:launched in hubli on 11/09/2011.






GULABI - bunglow project launched in Mangalaore





To set up CEMENT BLOCK MANUFACTURING FACTORY in Mangalore. commercial production expected begin by August 2011"





"Mr.Praveen Kumar is Promoted and Transferred to Hubli as Regional Manager w.e.f 01/06/2011. we wish him all The Best"




:Launched in Mangalore, which will be the trading arm of in building materials such as tiles and sanitarywares



: Plumbing and Electrical Work Underway.


: Brickwork Completed.

: All Slabs Completed. Brickwork Underway.


T3 Sugandhi-Shimoga Plinth Work Underway.

: Plaster will be completed on 30/10/10

: shimoga-sugandhi scheduled for launch on 9/10/10

: 4th slab completed on 24/9/10

: All slabs completed on 21/9/10

: All the slabs and brickwork completed.
Plaster is expected to be completed by 10/9/10.
    

   : 3rd slab is completed. 4th slab will be
ready by 26/9/10.

: 3rd slab will be completed by 26/9/10.


: plinth is completed on 10/4/2010


: raft foundation completed on 27/3/2010

: 2nd slab is completed on 27/03/2010.

We are glad to announce that all the apartments in are sold.

 
     
 